Donate Now Lake Country work continues (southern Kal Lake, Isthmus and Wood Lake)

Construction
Begins

March 1

Construction
Ends

May 31
Starting at 12km
Ending at 28km

Next trail entrance: There is no access in Lake Country - entire section is closed due construction and permitting

Work is underway again thanks to warmer weather. Laying of the crushed aggregate will continue as well as final grading. Conversion of the bridge on the isthmus from railway to pedestrian/bicycle use will continue through April and May. Work on the trail/road intersections will also be completed this spring.

The permit process for the trail is an important aspect to the trail in Lake Country and is also not completed. The ALC is meeting with adjacent property owners to ensure that the operation of the trail will not interfere with agricultural activities adjacent to the trail and that trail users will be safe during the growing season. Please respect this request not to use the trail until the trail and safety requirements have been finalized and installed, and the permit to operate given.

Just prior to the trail opening, waypoint and safety signage will be installed.

Posted on March 1, 2018

Campaign Progress

It will take a community to build a legacy.

Current Target

70% Complete

70%7,800,000

48.5 km Funding Goal

70% Complete

34.50 (70%) total kilometres funded

4766individual
donors

43trail
ambassadors

23campaign
partners

61business
partners

Donate Now

Funding totals are not automatically updated after your donation, please check back regularly for updates.